Q2D / FS-01 Audit review pack

Illustrative program · Synthetic data · No actual approvals or shipments

Version 1.0 · 2026-09-10 · Diagnostic snapshot: Quotes & award · Prepared as an example by Q2D

Executive readout

A North American edge-AI team is planning a 100-kit outdoor power pilot. The kit combines flexible PV, a charge controller, battery with BMS, regulated output and an installation harness. This functional description is not a sized electrical design. No power, capacity, runtime, lifetime or certification result is assumed.

The immediate decision is whether supplier quotations provide a consistent basis for qualification and award. Supplier A references connector A, while RFQ R1 requires connector drawing B. Supplier B references B and test scope T1, with tooling separately itemized. The team must reconcile these conditions before committing spend. No supplier has been selected in this diagnostic snapshot.

1. Operating baseline

RecordReferenceCurrent meaning
Requirement briefBaseline AInput to RFQ; engineering owns operating requirements
ConfigurationBOM B / connector drawing BRFQ reference, not trial-build release
Shared inquiryRFQ R1 / test scope T1Supplier exceptions remain visible
Quantity100-kit pilot planNo completed order or shipment

2. Risk and decision register

IDOpen conditionDecision ownerNext action / closure evidence
R-01Supplier A connector mismatchClient engineeringObtain QA-R2 against drawing B and assess qualification evidence
R-02Unstated test and tooling assumptionsClient commercial owner + engineeringObtain itemized scope and T1 acknowledgement; record exclusions
R-03Trial-build release not establishedClient design authorityReview EC-01 and sample verification before releasing BOM B

All three risks remain open in this Audit snapshot. Due dates are agreed with the actual project team, not invented in this example. Q2D coordinates follow-up; suppliers provide corrected information and qualification evidence; the client makes technical and commercial decisions.

3. Quote decision memo

BasisSupplier ASupplier B
Connector revisionA · mismatchB · RFQ basis
ToolingExcludedSeparate line item
Test coverageNot statedT1 referenced

Recommendation: obtain corrected quotation QA-R2 and the qualification evidence, then review both offers on RFQ R1. The recommendation is not a supplier award or purchase order. No invented price, savings or delivered lead time is included. Q2D service fees remain separate from supplier charges.

BOM-01 / Approved RFQ reference

BOM B / drawing B · Owner: Client engineering

RFQ R1 requires connector drawing B. The accepted quote must identify the same interface, quantity basis and test scope. No supplier has been awarded in this initial snapshot.

QA-01 / Supplier A quotation

QA-R1 · exception · Owner: Supplier A

References connector A. Tooling is excluded and test coverage is unstated. Request a corrected quote and qualification evidence before evaluating commercial suitability.

QB-01 / Supplier B quotation

QB-R1 · conditional · Owner: Supplier B

References connector B and T1; tooling is separately itemized. Technical qualification and client commercial approval remain required. No cost or delivery savings are claimed.

4. Illustrative 90-day action plan

Planning windowWorkOwner / gate
Days 0–30Reconcile quote references, tooling and test assumptionsQ2D follows up; suppliers correct; client engineering reviews
Days 31–60Assess sample evidence and commercial optionsClient technical and commercial decisions before commitment
Days 61–90Plan trial release and agreed implementation workOnly after scope, change and verification gates are met

These are planning windows, not promised execution dates. Missing evidence, supplier timing or client review can change the sequence. Trial production, corrective work, freight and supplier costs are not automatically included in an Audit.

Handoff and acceptance

Review the agreed questions, document references, open conditions and proposed actions with technical and commercial owners. Acceptance criteria and review participation are agreed in the engagement scope. Choose internal execution, a scoped Sprint or an Annual Pod; the Audit does not require subsequent purchase.

Deliverable index

01 / Operating baseline

A versioned view of requirements, BOM, suppliers and the evidence available today.

02 / Risk & decision register

Open conditions, impact, owner and the evidence needed for the next decision.

03 / Quote decision memo

Comparable assumptions, supplier exceptions and a recommendation for client review.

04 / Executive readout & 90-day plan

Prioritized actions, dependencies and a clear handoff to your team or a scoped engagement.

Later lifecycle scenes — outside this diagnostic snapshot

The website also contains independent, synthetic NPI, quality, shipment and field-feedback scenes. Their sample approvals and records are not evidence available at the diagnostic time above. They demonstrate how the operating record could continue; they are not actual customer results or Audit execution deliverables.

Use of this sample

Use this document to review the format of Q2D work. Do not use the synthetic configuration as a production design, quotation, purchase order or approval. All technical requirements, verification criteria and commercial scope require the relevant client authority.